Modular Homes - Faster and Better
The table below will show you how much time you will save when you build a modular home with Custom Modular Designs. The modular home building completion times are estimates based on a typical modular home. The actual modular home completion times will depend on a number of factors including the size and style of the modular home that you choose to build.
For example, smaller modular homes require less finish time than larger modular homes and more intricately designed modular homes are timelier to finish than basic modular homes. Site built homes generally require more site related work, more inspections, and more sub-contractors than our modular homes. Therefore, site built homes generally take 2 to 3 times longer to complete than our modular homes. The BOLDED colored boxes show the parts of the project completed at our factories.
| Project Step - (In normal order) | Site-Built | Modular-Built |
|---|---|---|
| Stake the lot and house | 1 - 3 hours | Same |
| Clearing & Excavation | 1 - 3 days | Same |
| Utilities, temporary service, a portable toilet & a trash bin | 1 - 3 hours | Same |
| Footings. First inspection must be made before pouring | 1 day | Same |
| Foundation and soil treatment, then foundation survey | 1 week | Same |
| Rough-ins for plumbing | 2 - 4 days | Same |
| Slabs, basement, and garage | 1 - 2 days | Same |
| Framing and drying-in | 1 - 3 weeks | Factory Process |
| Exterior siding, trim, veneers | 1 - 3 weeks | Factory Process (partial, no gable ends or upper floors) |
| Chimneys | 2 days - 1 week | Same (except framed chimneys and chases are completed at our factories) |
| Roofing | 2 days - 1 week | Factory Process (some roofing may be completed on site depending on the type of roof) |
| Plumbing and Electrical rough-ins | 1 - 2 weeks | Factory Process |
| Insulation | 3 days | Factory Process (some insulation will need to be installed on site - i.e. basement) |
| Drywall (seamed and taped) | 2 weeks | Factory Process |
| Interior trim and cabinets | 1 - 2 weeks | Factory Process |
| Painting | 2 - 3 weeks | 1-2 weeks (most of the prep work is completed at our factories) |
| Other trims such as granite, corian or ceramic tile, vinyl floors | 1 day - 1 week | Same |
| Finishing plumbing, mechanical, electrical and hooking up utilities | 1 - 2 weeks | Factory Process (partial) (hook-ups and connections between boxes are completed on site - 2 to 4 days) |
| Cleanup | 2 - 3 days | Same |
| Carpet and/or hardwood floor finish | 3 days - 1 week | Carpeting - Factory Vinyl - Factory Laminate - Factory Tile (some) - Factory Hardwoods - on site |
| Driveway/Landscaping | 1 week | Same |
| Final inspections, surveys, and closing of loan(s) | 1 - 3 days | Same |