Modular Homes - Faster and Better

The table below will show you how much time you will save when you build a modular home with Custom Modular Designs. The modular home building completion times are estimates based on a typical modular home. The actual modular home completion times will depend on a number of factors including the size and style of the modular home that you choose to build.

For example, smaller modular homes require less finish time than larger modular homes and more intricately designed modular homes are timelier to finish than basic modular homes. Site built homes generally require more site related work, more inspections, and more sub-contractors than our modular homes. Therefore, site built homes generally take 2 to 3 times longer to complete than our modular homes. The BOLDED colored boxes show the parts of the project completed at our factories.


Project Step - (In normal order) Site-Built Modular-Built
Stake the lot and house 1 - 3 hours Same
Clearing & Excavation 1 - 3 days Same
Utilities, temporary service, a portable toilet & a trash bin 1 - 3 hours Same
Footings. First inspection must be made before pouring 1 day Same
Foundation and soil treatment, then foundation survey 1 week Same
Rough-ins for plumbing 2 - 4 days Same
Slabs, basement, and garage 1 - 2 days Same
Framing and drying-in 1 - 3 weeks Factory Process
Exterior siding, trim, veneers 1 - 3 weeks Factory Process
(partial, no gable ends or upper floors)
Chimneys 2 days - 1 week Same
(except framed chimneys and chases are completed at our factories)
Roofing 2 days - 1 week Factory Process
(some roofing may be completed on site depending on the type of roof)
Plumbing and Electrical rough-ins 1 - 2 weeks Factory Process
Insulation 3 days Factory Process
(some insulation will need to be installed on site - i.e. basement)
Drywall (seamed and taped) 2 weeks Factory Process
Interior trim and cabinets 1 - 2 weeks Factory Process
Painting 2 - 3 weeks 1-2 weeks
(most of the prep work is completed at our factories)
Other trims such as granite, corian or ceramic tile, vinyl floors 1 day - 1 week Same
Finishing plumbing, mechanical, electrical and hooking up utilities 1 - 2 weeks Factory Process (partial)
(hook-ups and connections between boxes are completed on site - 2 to 4 days)
Cleanup 2 - 3 days Same
Carpet and/or hardwood floor finish 3 days - 1 week Carpeting - Factory
Vinyl - Factory
Laminate - Factory
Tile (some) - Factory
Hardwoods - on site
Driveway/Landscaping 1 week Same
Final inspections, surveys, and closing of loan(s) 1 - 3 days Same